To Configure
Non-Graphic Components from InstrumentIndexList for Work Packaging
To Import the
InstrumentIndex_<ProjectName>.xlsx Data
In
eB Director, go to the SystemAdmin pane and
check out the InstrumentIndex.xml mapping file from the Bulk Import of Excel
Spreadsheets template.
Go to the eBCheckout
location on your desktop and replace the InstrumentIndex.xml with the one from
the …\CSST\ExcelMappingFiles\Tags\InstrumentIndex.xml and then check in the
changes.
Back in your project in
ConstructSim Work Package Server, go to the
Project info panel > Project data and choose the Bulk upload tab.
Click the Upload button.
Browse to and select the
…\ProjectData\Instrument Index\InstrumentIndex_<ProjectName>.xls file.
After uploading, set the
List Type property to Instrument Index and the Mapping property to
InstrumentIndex.xml.
Check the
InstrumentIndex_<ProjectName>.xls checkbox and choose Start Import.
To Configure
End-To-End Data Run Workflow to Process
InstrumentIndex_<ProjectName>.xlsx into Component Data
With
ConstructSim Executive, open the project
workflow (.vem).
Expand the End-To-End Data
Run > Phase 2 – Populate New VCM with Latest Engineering Data >
Engineering Lists > Generate Engineering Components and Synchronize node.
Make a copy of the
Generate Components from Lists Managed Command at the same level.
Disable the original one
if it is not already disabled.
Right-click on your new
copy of the Managed Command and choose Properties.
Edit to include
Instrumentation in the name; then set the DISCIPLINESLIST attribute value to
Instrumentation.
Configure
End-To-End Data Run Workflow to Process Instrumentation Construction
Tasks
Copy the End-To-End Data
Run > Phase 2 - Populate New VCM with Latest Engineering Data > Task
Processing > Task Generation > STANDARD - Generate Tasks Using Generic
Unit Rates > STANDARD - Generate Generic Electrical Unit Rates node to the
same level.
In the copied Managed
Command:
Rename the workflow
node to STANDARD – Generate Generic Instrumentation Unit Rates.
Delete the Create
NodeOutputs for Tray Components and Create NodeOutputs for Conduit Components
nodes.
Edit the Create
NodeOutputs for Instrument Components node’s PS_ATTRIBUTEVALUE to
INSTRUMENTATION.
Rename Create
Electrical Construction Tasks Using Generic Unit Rates to Instrumentation and
set the UNITRATEFILE attribute value to the [ProjectData] -
.\UnitRates\InstrumentationURT_<ProjectName>.mdb file.
Enable the Managed
Commands under the workflow node.